Water Line Extension Hinson Mosely Road to Camden Street
City of Jesup
Project Details
T. R. Long Engineering, P.C. prepared a complete set of construction plans and permit documents, in accordance with the Georgia Department of Transportation and the City of Jesup’s criteria, for the extension of an 8” water main. The work included construction of approximately 0.50 miles of an 8” water main, along State Route 84, that extended from Hinson Mosely Road to Camden Street. The project included extending the existing water main across commercial driveways and streets while maneuvering around the existing storm drainage systems and utilities. Responsible for initial site survey, plan preparation, and design and permitting.